Re-Heat Furnace Waste Heat Recovery System
Client: NatSteel
Location: Singapore
Project Includes:
- Installation of ORC system
- Single RHF application
- Direct Heat Exchange ORC
- Power production: up to 0.6 MW
- Cooling system design
- Layout and ductwork optimization
Project Outcome:
- Construction completed within 17 months after receipt of order (ARO).
- Zero reported accidents or incidents.
- Commissioning and start-up period January 2013.
Project History
Conceptual Engineering
Basic & Detailed Engineering
Procurement & Construction
Start-up
2010
2011 – 2012
2012
Jan 2013