Rotary Kiln 4 Off Gas Upgrade Study and Basic Design
New Rotary Kiln ESP System

Rotary Kiln 4 Off-Gas Upgrade Study and Basic Design

Client: PT Vale

Location: Indonesia

Conceptual Study and Basic Engineering to Upgrade Kiln 4 ESP system to meet 50 mg/Nm3.

  • System capacity increase evaluation
  • Evaluate impact of multiple fuel and reductant options
  • Evaluate options for providing increased capacity and improved dust removal performance:
    • Modify or replace existing multiclone
    • Modify or replace existing ESP
    • Build in current location or adjacent
Project History

Scoping Study
Basic Design

September 2013
December 2013

Electric Smelting Furnace Off Gas System DesignCopper Smelter Emissions Reduction Study